EPCs PROJECT PROGRESS UPDATES

 

 

Duqm Refinery project is making a steady progress in all EPCs. Below is a sum up of the current works ongoing in the EPCs :

 

WEEK ENDING 26/JUNE/2019

 

DEPOT CONTROL BUILDING FOUNDATION WORKS

 

PIPERACK PR530 002

PRU530 002 B,C                                                                                                 PRU530 002 A

 

LCS #11 SUNKEN SLAB CONTAINMENT WALL WORKS

 

FFI #2 SLAB POUR WORKS 24TH /25TH/06

 

LPG BULLET TANK RETAINING WALL WORKS

 

TK710 007B 2ND COURSE ERECTION

 

PR530 01 SECTION E, F & J ERECTION

 

ADMIN BUILDING GRADE TO 1ST COLUMN WORKS

 

SS660 GRADE BEAM AND COLUMN WORKS

 

PRS MODULE #1, #2 & #4

 

440PK 002 A & B BOILER FOUNDATIONS

 

FFI #1 SLAB REINFORCEMENT WORKS

 

S400 FOUNDATION WORKS

 

COOLING TOWER BASIN SLAB REINFORCEMENT WORKS