EPCs Project Progress Updates
EPCs Project Progress Updates

Duqm Refinery project is making a steady progress in all EPCs. Below is a sum up of the current works ongoing in the EPCs :
WEEK ENDING 26/JUNE/2019
DEPOT CONTROL BUILDING FOUNDATION WORKS
PIPERACK PR530 002
PRU530 002 B,C PRU530 002 A
LCS #11 SUNKEN SLAB CONTAINMENT WALL WORKS
FFI #2 SLAB POUR WORKS 24TH /25TH/06
LPG BULLET TANK RETAINING WALL WORKS
TK710 007B 2ND COURSE ERECTION
PR530 01 SECTION E, F & J ERECTION
ADMIN BUILDING GRADE TO 1ST COLUMN WORKS
SS660 GRADE BEAM AND COLUMN WORKS
PRS MODULE #1, #2 & #4
440PK 002 A & B BOILER FOUNDATIONS
FFI #1 SLAB REINFORCEMENT WORKS
S400 FOUNDATION WORKS
COOLING TOWER BASIN SLAB REINFORCEMENT WORKS